Primat Construction v Nelson Mandela Bay Metropolitan Municipality (1075/2016) [2017] ZASCA 73 (1 June 2017)
Where a party to a contract repudiates it, the aggrieved party has an election to abide by the contract and enforce its performance: if that election is exercised, but the defaulting party nonetheless persists in the breach by evincing an unequivocal intention not to remedy the breach, the aggrieved party, after affording the defaulting party the oportunity to repent of the repudiation, may change the election and cancel the contract and claim damages.